there r 2 groups of worker.. skilled n partially skilled. if both group work togather they nid 30 days to finish the job. if partially skilled worker can oni do 2/3 of the skilled worker did in a day. how many days needed if only partially skilled worker is workin to finish the job? 3 T$ C/ g; |7 [ }; l+ w/ cTVBNOW 含有熱門話題,最新最快電視,軟體,遊戲,電影,動漫及日常生活及興趣交流等資訊。A.50 % Z6 g, o& H9 F9 [# L- `B.60 + z8 ^) Q) `# L- m+ i2 a- Uwww2.tvboxnow.comC.65 2 u2 Q) \3 y, d* VD.75作者: genzo2106 時間: 2007-9-12 01:52 PM
answer is D:75作者: Alan8166 時間: 2007-9-12 03:37 PM
answer is D:75作者: dokho 時間: 2007-9-16 12:13 AM
D FOR DOG作者: ken87 時間: 2007-9-16 01:01 AM 標題: 回復 #1 nelston 的帖子